Dependencies can be turned on or off for your organization. When dependencies are on, you can also enable an optional validation rule that prevents tasks from being completed when their predecessors are incomplete.
Enable or Disable Dependencies [Admin]
- From Setup, navigate to:
- Lightning: Custom Code | Custom Settings.
- Classic: Develop | Custom Settings.
- Click Manage next to TaskRay Global Settings.
- To toggle Dependencies on/off, check/uncheck the Enable Multiple Dependencies checkbox.
- Click Save.
Important! TaskRay with Dependencies enabled will overwrite existing project start and end dates for projects that contain tasks with start and end dates. Dependencies will automatically calculate start and end dates based on the records in the project, including tasks and sub-projects.