Prevent the Completion of a Task When its Predecessor is Incomplete

This feature is available to the following product editions
  • Starter
  • Standard
  • Premium

TaskRay comes with an optional validation rule that can be turned on to prevent the completion of a task until all of its dependent predecessor tasks are complete. Dependencies must be enabled in order for the validation rule to work.

With the rule activated, users will not be able to finish a task before all dependent predecessor tasks are completed (moved to the Finished column). To learn more about establishing dependency relationships between tasks, see this article on multiple dependencies

 

Prevent the Completion of a Task when its Predecessor is Incomplete [Admin]

  1. From Setup, navigate to:
  • Lightning: Objects and Fields | Object Manager.
  • Classic: Create | Objects.
  • Select TaskRay Task.
  • Scroll down to the Validation Rules section and click Edit next to Prevent_Complete_If_Dependent_Incomplete.
  • Select the Active checkbox.
  • Click Save.
  • Was this article helpful?

    9 out of 10 found this helpful

    Have more questions? Submit a request